CRRC Subsidiary’s Wind Turbine Blade Factory in Khánh Hòa Reaches 88.4% Completion

A CRRC subsidiary said on November 23 that construction of the main production building at its wind turbine blade factory in Khánh Hòa, Vietnam, was 88.4% complete. The project plans eight production lines with a designed annual capacity of 480 sets of blades and aims to produce blades up to 150 meters long.

VietVance

1 min read

On November 23, CRRC subsidiary Zhuzhou Times New Material Technology announced that construction of the main production building at its wind turbine blade factory in Phước Nam Industrial Park, Khánh Hòa Province, Vietnam, was 88.4% complete. The building’s steel structure, roof and exterior enclosure have been completed, while supporting facilities remain under construction.

Illustrative image accompanying the report on the wind turbine blade factory being built in Vietnam by a CRRC subsidiary.(VietVance)

Project documents discussed by Khánh Hòa provincial leaders and the investor in July 2025 show that the factory will cover approximately 31.46 hectares. It is planned to have eight production lines for 110-meter wind turbine blades, with a designed annual capacity of 480 sets. The project is also intended to be capable of producing blades up to 150 meters long.

CRRC said this is the first overseas factory that Zhuzhou Times New Material Technology has independently invested in, built and operated. A wholly owned subsidiary is responsible for the project. Under a capital increase plan announced in November 2025, the subsidiary’s registered capital would rise to approximately 1.7 trillion Vietnamese dong, equivalent to about US$64.675 million at the exchange rate used when the plan was announced. In September 2026, CRRC said the factory would serve Vietnam and other Southeast Asian markets and help address the supply and transport of large wind power components.

The company has previously produced wind turbine blades longer than 100 meters in China. In December 2024, it announced the production of a 118-meter onshore wind turbine blade in Jiangsu. In May 2026, it announced the completion of a 110-meter recyclable blade at its Sheyang factory. Those products were manufactured in China, not at the Khánh Hòa factory. The company said batches of wind turbine blades made at the Sheyang factory have been shipped to Vietnam since 2020.