Da Nang Approves Investment in Phase 1 of Tam Anh 3-Indusvalley Industrial Park
Da Nang approved investment in the 238.11-hectare first phase of Tam Anh 3-Indusvalley Industrial Park on November 25, 2026. The project has an investment value of VND 2.479 trillion and is expected to begin attracting investors in the third quarter of 2027. Infrastructure construction and the start of operations are scheduled through the second quarter of 2031.
On November 25, 2026, the Chu Lai Open Economic Zone Management Board approved the investment policy and investor for phase 1 of the Tam Anh 3-Indusvalley Industrial Park project. Located in Tam Anh Commune, Da Nang, the 238.11-hectare project will be developed and operated by Indusvalley Chu Lai Joint Stock Company.

A rendering of an industrial park project in Da Nang.(VietVance)
The project has a total investment of VND 2.479 trillion, comprising VND 495.8 billion in investor equity, or 20%, and VND 1.9832 trillion in mobilized capital, or 80%. Its operating term is 70 years from the date the investment policy and investor were first approved. The project will develop and operate industrial park infrastructure and provide industrial real estate, warehousing and transport support services.
Under the plan, basic construction will be completed and the project brought into operation within 48 months of the state allocating or leasing the land. The investor plans to complete investment preparations and related legal procedures from the fourth quarter of 2026 to the first quarter of 2027. Compensation, site clearance and land handover are scheduled from the first quarter of 2027 to the first quarter of 2030. Infrastructure construction and the start of operations are scheduled from the second quarter of 2027 to the second quarter of 2031, with the project expected to begin attracting investors in the third quarter of 2027.
The management board requires the investor to comply with regulations on investment, land, construction, environmental protection and real estate business. Before the project begins operating, the investor must also provide land for worker accommodation and public service facilities, and meet infrastructure, occupational safety and fire safety requirements. Relevant departments and the Tam Anh Commune government will help guide, inspect and supervise implementation.
Source: VietVance