Lâm Đồng Expressway Project Has Investment of About VND 18.945 Trillion

Construction is underway on five major packages of the Bảo Lộc–Liên Khương Expressway in Lâm Đồng. By mid-November 2026, 95.56% of the required land had been handed over, while disposal sites and local construction material supplies remained insufficient. The project is scheduled to be completed and enter service in the fourth quarter of 2028.

VietVance

1 min read

Construction is underway on the Bảo Lộc–Liên Khương Expressway in Lâm Đồng Province, with contractors deploying workers and equipment across five major packages. The public-private partnership project is 73.62 km long, passes through 10 communes and wards, and has a revised total investment of about VND 18.945 trillion.

By mid-November 2026, Lâm Đồng Province had handed over 593.58 hectares of land ready for construction, or 95.56% of the 621.128 hectares required for the project. Nearly 99% of the funds allocated for land acquisition compensation in 2026 had been disbursed. However, authorized disposal sites along the route meet only about half of the demand, and local construction material quarries have yet to meet the project's needs.

Construction site of the Bảo Lộc–Liên Khương Expressway in Lâm Đồng Province.(VietVance)

On the section through Tân Hội Commune, workers and machinery are concentrated on sites ready for construction. At the Núi R’Chai interchange, Construction Corporation No. 1 (CC1) is preparing the foundations and building the interchange ramps. Mai Văn Thái, head of the construction site for the company's Package 04, said the contractor increased equipment and staffing after receiving land ready for construction and arranged continuous work in three shifts with four crews.

On the section through Gia Hiệp Commune, Công ty Cổ phần Đầu tư và Xây dựng Giao thông Phương Thành is casting beams, excavating and filling the roadbed, drilling foundation piles, and building culverts and local access underpasses. It has deployed more than 300 personnel across 10 work fronts operating continuously and installed an on-site concrete batching plant. The expressway is designed with four lanes in both directions, a 24.75-meter-wide roadbed, a design speed of 100 km/h and continuous emergency stopping lanes. The project aims to open to traffic on a trial basis in the third quarter of 2028 and be completed and enter operation in the fourth quarter.