Long Thanh Airport Targets December 24 Opening, With Four Contracts at Risk of Delay

Long Thanh Airport in Dong Nai is scheduled to begin commercial operations on December 24, 2026. The Ministry of Construction says substantial work remains on four contracts, including the passenger terminal and internal roads. The opening date will depend on construction progress, operational trials, inspections and permits.

VietVance

2 min read

Long Thanh Airport in Dong Nai is scheduled to begin commercial operations on December 24, 2026. The Ministry of Construction says the opening plan proposed by ACV would allow the project to deliver benefits sooner, but substantial work remains on some facilities, so the opening date must be determined by actual progress. As of the end of October, components 1, 2 and 4 were on track to meet the December operational readiness target. The main challenge lies with component 3, which covers the airport’s essential facilities.

Exterior of Long Thanh Airport’s passenger terminal on November 17, 2026.(VietVance)

Component 3 has 16 contract packages: four are complete and 12 remain under construction. Substantial work remains on four packages covering internal airport roads and technical infrastructure, the passenger terminal, cargo terminal No. 1 and its supporting facilities, and the parking structure. This could affect completion deadlines. Some work also faces construction material supply and contractor payment issues. The relevant packages must be completed in November so facilities in other components can be connected and inspected.

Operational readiness preparations run in three rounds from September to December, with 55 trial scenarios. The Ministry of Construction says preparations for a large airport must test how the entire system works together; comprehensive integrated testing at Long Thanh is expected to last only about three months. Because construction, equipment calibration, staffing and administrative procedures must proceed at the same time, the short testing period leaves less time to identify and fix faults.

The baggage handling system at Long Thanh Airport.(VietVance)

The Ministry of Construction has asked ACV to reassess the December opening plan and determine the scope of operations based on the overall completion of construction, inspection and trial operation results, safety assessments and licensing procedures. Vietnam’s Standing Deputy Prime Minister Phạm Gia Túc has instructed relevant agencies to help resolve payment, fuel and material supply issues and accelerate construction of roads connecting to the airport.

ACV previously planned for the airport to handle up to 366 flights a week in its initial phase, including 322 domestic and 44 international flights. A Civil Aviation Authority of Vietnam survey of airlines and other stakeholders found that international carriers support moving to Long Thanh, but many want to delay the move until the 2027 winter flight schedule or later. The airport’s first phase is designed to handle 25 million passengers and 1.2 million tonnes of cargo and mail annually.

Source: VietVance