Construction Lags on Nghệ An Expressway Project Costing Nearly VND 2.4 Trillion
Nearly six months after work began on an expressway project in Nghệ An province with an investment of nearly VND 2.4 trillion, several construction packages are behind schedule. On November 15, the provincial chairman called for faster work and completion of the remaining land handover, and said contracts with persistently delayed or underperforming contractors could be terminated.
On November 15, Nghệ An provincial chairman Võ Trọng Hải chaired a meeting to review construction progress on the Vinh–Thanh Thủy Expressway project. Construction began on May 18, 2026. The project has a total investment of nearly VND 24 trillion and runs approximately 60.03 kilometers through nine communes in Nghệ An province. Figures released by the provincial transport project management authority show that work completed under several contract packages still accounts for a small share of their contract values.
The 6.3-kilometer XL01 package has 19 active construction fronts. Work completed is valued at nearly VND 172 billion, or about 6% of its VND 2.89 trillion contract value. All land has been handed over for the 24.8-kilometer XL02 package, which has 34 construction fronts, but work completed is valued at more than VND 151 billion, or about 3% of its VND 5.094 trillion contract value. Work completed on the XL03 package, which is more than 19 kilometers long, is valued at about VND 63 billion, or 1.2% of its contract value. Site preparation is still underway for XL04 and XL05, while approval of XL06 is expected to be completed in November.

Construction is progressing slowly on several packages of the Vinh–Thanh Thủy Expressway project.(VietVance)
Land handover has been completed for approximately 59.4 kilometers, or 99% of the project, with about 550 meters still to be handed over. Issues involving the relocation of technical infrastructure, the allocation of spoil disposal sites, material supplies and resettlement remain unresolved. Võ Trọng Hải called for the procedures to allocate spoil disposal sites to be completed by November 25, 2026, and for construction access roads and all land handover to be completed by November 30. Contractors must provide all necessary machinery and equipment for construction fronts that have yet to start by early December at the latest.
Nghệ An provincial leaders said they would consider strict action against contractors responsible for prolonged delays, lacking capacity or failing to honor their commitments. Measures could include terminating contracts, taking back portions of the work and assigning them to capable firms. XL01 is being built by a consortium of Tập đoàn Đèo Cả and CTCP Xây lắp Thương mại Delta; six contractors, including Tập đoàn Sơn Hải, are involved in XL02.

Nghệ An province has called on the project's contractors to accelerate construction.(VietVance)
Source: VietVance