Ngọc Hồi Bridge Begins Girder Installation as Land Handover Remains Incomplete in Hưng Yên
The first prefabricated girders have been installed on Ngọc Hồi Bridge, linking Hanoi and Hưng Yên, while construction output has reached 26.98% of the contract value. About 0.53 hectares in Hưng Yên remain to be handed over, and some power, water and communications facilities still need to be relocated, potentially affecting further construction.
The Ngọc Hồi Bridge project, linking Hanoi and Hưng Yên, has entered the girder installation stage. Project managers said construction began on August 19, 2025, and work is now underway at 18 sites simultaneously. The first prefabricated Super T girders have been installed on piers on the Hưng Yên side, while foundation and pier work is progressing on the main bridge across the Red River.

Contractors have deployed workers and equipment at the Ngọc Hồi Bridge construction site to advance multiple parts of the project.(VietVance)
As of the original article’s publication, 2,201 of 2,315 bored piles and 196 of 328 pile caps had been completed for the approach bridges. A total of 503 prefabricated Super T girders had been cast, of which 140 had been installed. Construction output across the project stood at VND 1.98845 trillion, equivalent to 26.98% of the VND 7.37072 trillion contract value; the figure excludes contingency costs.
The bridge and its approach roads have a total length of about 7.5 kilometers, including approximately 5.2 kilometers in Hanoi and 2.3 kilometers in Hưng Yên. The main bridge across the Red River is about 680 meters long and is designed with six motor vehicle lanes and two mixed traffic lanes. Total investment in the project is VND 10.197833 trillion. Once completed, the bridge is expected to improve travel between Hanoi and Hưng Yên and connect with nearby expressways and national highways.

The first prefabricated Super T girders have been installed on the bridge piers, marking the start of work on the superstructure.(VietVance)
Land handover remains an obstacle to construction. The project requires about 55.26 hectares of land, all 32.6 hectares of which have been handed over in Hanoi. In Hưng Yên, 22.13 hectares have been handed over, or about 97.6% of the land needed in the province, leaving approximately 0.53 hectares outstanding. The remaining land involves 23 plans concerning residential and defense land. Some 22 kV power lines, water supply pipes and communications facilities have also yet to be relocated. Project managers have urged the authorities in Văn Giang commune, Hưng Yên province, to speed up site clearance and the relocation of these facilities.