Phu Quoc Accelerates Construction of 21 Key APEC Projects
An Giang province and the Phu Quoc special zone are advancing 21 key projects for APEC 2027. Phu Quoc International Airport’s second runway began commercial operations in late July 2026. Work continues on terminals, a convention center, roads, light rail and hotels, with An Giang aiming to complete the APEC facilities before June 30, 2027.
Vietnam’s An Giang province and the Phu Quoc special zone are advancing 21 key projects for APEC 2027. The second runway at Phu Quoc International Airport, 3,300 meters long and 45 meters wide, began commercial operations in late July 2026. The new runway meets the International Civil Aviation Organization’s Code E standard and allows the existing runway to be extended to 3,500 meters without shutting down the entire airport.

Phu Quoc International Airport’s second runway has gone from a construction site to a runway in commercial operation.(VietVance)
As of late October 2026, about 95% of the T2 terminal’s main concrete structure, 90% of its two wings and all of its main steel roof had been completed. About 75% of the automated baggage handling system, which extends more than 8 kilometers, was complete, with sections undergoing trial operation. T2 is expected to begin operations in 2027. The VIP terminal for APEC delegations had also completed its concrete structure by then, while its steel structure and roofing were about 95% complete. It is scheduled for completion by the end of March 2027.
By early November 2026, the APEC Convention and Exhibition Center’s steel structure and metal roofing were complete, while work continued on its facade, mechanical and electrical systems, and interiors. The center has a total floor area of about 153,100 square meters, including an 11,050-square-meter event space. A nearby multipurpose performance venue with 4,030 seats had completed more than 98% of its reinforced concrete structure.

The APEC Convention and Exhibition Center’s wave-shaped roof structure has taken shape.(VietVance)
For transport infrastructure, the 19.26-kilometer expansion of provincial road ĐT.975 had completed about 50% of its roadbed and 65% of its utility trenches, with a target of opening the full route in the second quarter of 2027. The double-track light rail line linking the airport with the south of the island is 17.59 kilometers long. At the time of reporting, more than 11 kilometers of track had been laid out of approximately 35 kilometers of single-track rail to be installed. The first trains are expected to arrive on Phu Quoc Island between January and February 2027 for installation, inspection and trial runs.
A hotel project in the south of the island funded by Sun Group covers 88.4 hectares and includes plans for 17 seafront hotels, with nearly 7,000 rooms expected in the first phase. By early November 2026, some hotel buildings had reached 22 and 32 stories. An Giang province plans to complete the APEC facilities before June 30, 2027.
Source: VietVance