Phu Quoc light rail project lays over 11 km of track, targets November 2027 opening
The Phu Quoc light rail project has laid over 11 km of track, and four stations are about 60% complete. Funded by Sun Group, the line will connect Phu Quoc International Airport with the APEC Convention and Exhibition Center and tourist areas in the island’s south. Trial operations are planned for July 2027, followed by commercial service in November.
Over 11 km of track has been laid for the Phu Quoc light rail project. Construction began on December 19, 2025. Sun Group is investing in the project under a build-operate-transfer (BOT) arrangement, with total investment of nearly VND 9 trillion. The 17.59 km line will connect Phu Quoc International Airport with the APEC Convention and Exhibition Center and resorts and entertainment facilities in the island’s south.
The line is planned to have six stations, with approximately 1.3 km of elevated track, 14.3 km at ground level and 2 km underground. According to Sun Group’s latest progress update, about 1,200 to 1,300 engineers and workers are on site, divided into seven construction teams; four stations are about 60% complete. Bored pile work for the bridges and tunnels is complete, and the tunnel leading to the airport has reached completion of its reinforced-concrete structure.

Construction site of the Phu Quoc light rail project. Photo: Sun Group.(VietVance)
High temperatures, sudden heavy rain and sea winds on the island have affected construction and the transport of materials. The handover of the construction site in separate sections has also made it harder to allocate equipment and workers. The project plans to complete the tunnel structures and box girders in December 2026 and finish laying track across the line in February 2027.
Sun Group is working with CRRC Dalian to develop the trains; a consortium of Vietnam Railways Corporation and China Railway 16th Bureau Group is responsible for supplying and installing the track. The trains are designed for hot, humid conditions and the island environment, with space for large luggage near the doors. The first trains are expected to arrive on Phu Quoc between January and February 2027.

Rendering of the Phu Quoc light rail project. Image: Sun Group.(VietVance)
The project plans to begin trial operations in July 2027 and commercial service in November. Initially, it is expected to use six to 10 three-car trains, with a projected line capacity of about 4,500 passengers per hour. Once in operation, the journey from the airport to the APEC Convention and Exhibition Center and tourist areas in the island’s south is expected to take about 20 minutes.