More Than 11 Kilometers of Rail Installed for Phu Quoc Light Rail Project

By the end of October 2026, more than 11 kilometers of rail had been installed for the Phu Quoc light rail project, out of approximately 35 kilometers planned. The 17.59-kilometer project has an investment of about VND 9 trillion and is intended to connect the airport, the APEC conference area and tourist destinations in the south of the island.

VietVance

2 min read

The Phu Quoc light rail project in Vietnam is 17.59 kilometers long, with an investment of about VND 9 trillion. It is being built under a BOT model, with state funding accounting for 70% and Sun Group contributing 30%. The planned route will connect Phu Quoc Airport, the APEC conference area and tourist destinations in the south of the island. Once completed, it will serve travel needs related to APEC 2027.

At the end of October 2026, work on the Phu Quoc light rail project’s tunnels, bridges, stations and tracks was progressing simultaneously.(VietVance)

As of the end of October 2026, Nguyễn Tất Đạt, head of the rail supply and installation contract package, said more than 11 kilometers of rail had been installed, out of approximately 35 kilometers planned. The site had seven construction fronts, with about 1,200 to 1,300 engineers and workers working on the roadbed, stations, bridges, tunnels and tracks. All bored piles for the bridges and tunnels had been completed, while construction of the main station structures was continuing.

By the end of October 2026, more than 11 kilometers of rail had been installed for the Phu Quoc light rail project.(VietVance)

The route is designed to minimize level crossings with roads, using overpasses or tunnels at intersections. Its design speed is 70 to 100 kilometers per hour, with a projected maximum capacity of 4,500 passengers per hour and a journey time of about 20 minutes between its termini. The initial plan calls for six to 10 clean-energy trains, each with three carriages. The line can accommodate up to 14 trains and will have a dedicated depot.

The project aims to complete the entire process from design and construction to the start of operations within 17 months. If achieved, this is expected to set a record for light rail construction time in Vietnam. Hồ Văn Mừng, chairman of the An Giang Provincial People’s Committee, said projects serving APEC remained on schedule and pledged that all would be completed before June 30, 2027.

Construction is underway on the underground sections of the Phu Quoc light rail project.(VietVance)

Source: VietVance