Vietnam’s First Pumped Storage Power Plant Has Excavated About 44% of Its Tunnels

The Bác Ái pumped storage power plant in Khánh Hòa Province has excavated about 7,600 meters of tunnels, or roughly 44% of the planned total. The 1,200 MW project aims to generate power from its first unit in December 2029. Contractors have passed through a fault zone longer than expected, and project managers say the overall schedule remains on track.

VietVance

2 min read

Underground construction continues at the Bác Ái pumped storage power plant in Vietnam’s Khánh Hòa Province. Project managers say that after more than 20 months of construction, seven work fronts have excavated about 7,600 meters of tunnels, or roughly 44% of the planned total length of about 17 kilometers. The project still aims to generate power from its first unit in December 2029, with the remaining units scheduled to begin generating in 2030. The entire project is expected to be completed in May 2031.

An aerial view of the Bác Ái pumped storage power plant project.(VietVance)

The project is funded by Vietnam Electricity Group, with total investment of about VND 21.101 trillion. It will have four generating units with a combined installed capacity of 1,200 MW. During periods of low electricity demand, the plant will pump water from the Sông Cái reservoir to an upper reservoir in the mountains; during peak demand, it will release the water to generate electricity. By design, the upper reservoir’s usable capacity of about 9 million cubic meters can support continuous generation for approximately seven hours.

Inside a tunnel under construction at the Bác Ái pumped storage power plant.(VietVance)

Tunnel construction has encountered changing geological conditions. The project management team’s technical lead said the design anticipated about 40 meters of poor geological conditions, but excavation revealed a fault zone extending 170 meters. Contractors had to excavate and reinforce the section in stages, adding about four months to the work on that section alone. Construction has now passed through the fault zone and entered more stable rock. Project managers say faster work in areas with better geological conditions has kept the overall schedule on track.

Workers labor day and night inside the mountain at the Bác Ái pumped storage power plant.(VietVance)

A visit to the site in early November found crews working in shifts around the clock. Project managers say about 400 construction personnel are currently on site, with the workforce expected to rise to about 700 during the next peak phase. Blasting and ventilation must be coordinated across several nearby tunnels, while contractors also face pressure to recruit and retain skilled workers.