A Southern Power Corporation executive said applications from data center projects in its service area have reached 4,000 MVA in recent months, urging careful assessment of their purpose and the strain they could place on the power system. Ministry of Industry and Trade calculations point to a risk of power shortages in the coming years.

VietVance

2 min read

At the “Energy for Sustainable Development” forum organized by the Vietnam Chamber of Commerce and Industry on November 19, Bùi Quốc Hoan, deputy general director of Southern Power Corporation (EVNSPC), called for careful assessment of the purpose of data center investments. He said Vietnam’s largest data center project under construction has a capacity of 140 MVA, while applications from such projects for power supply in EVNSPC’s service area alone have risen to 4,000 MVA in recent months.

Bùi Quốc Hoan, deputy general director of Southern Power Corporation, speaks at the forum on November 19.(VietVance)

Bùi Quốc Hoan said the scale of these applications far exceeds the needs of Vietnam’s domestic digital economy. Projects that serve domestic demand and support growth are justified; projects built solely to lease to foreign customers could take advantage of Vietnam’s lower electricity prices and put pressure on the security of the national power system. He said data center rental prices in Vietnam are significantly lower than those in Singapore and Taiwan because domestic electricity prices are lower.

According to Cushman & Wakefield, Vietnam’s data center supply is less than one-tenth that of Thailand and Malaysia. Ho Chi Minh City has 14 operating facilities with 33 MW of capacity, run by nine providers; its announced future supply stands at 68 MW. The article notes that Thailand and Malaysia have also begun tightening scrutiny of data center investment in recent months, with greater attention to projects’ actual economic contributions.

Pressure on electricity supply also underlies the call for scrutiny. According to Ministry of Industry and Trade calculations, without major changes to existing mechanisms, the power systems in northern Vietnam and across the country will face a risk of shortages: a capacity shortfall of about 4,300 MW is projected for 2027, potentially reaching 13,964 MW by 2030, with an electricity shortfall of about 61.2 billion kWh. Forum participants also called for improved financial mechanisms for liquefied natural gas power and offshore wind projects, along with investment in transmission infrastructure and energy storage.