Na Dương II Thermal Power Plant in Lạng Sơn Plans First Grid Connection on November 30
The Na Dương II thermal power plant in Vietnam’s Lạng Sơn province plans its first grid connection on November 30, 2026, and aims to begin commercial operations in early 2027. The project has an investment of VND 408.9 billion and a capacity of 110 MW. Civil works were more than 93% complete as of mid-November 2026.