BIWASE’s Ho Chi Minh City Waste-to-Energy Plant Set to Begin Operations in January 2027

BIWASE’s waste-to-energy plant in Ho Chi Minh City has an investment of about VND 1.15 trillion. Construction began on June 26, 2025. Its first phase will have 12 MW of generating capacity and is expected to process about 500 tonnes of waste a day. By mid-November 2026, several major components were 95% to 100% complete, with operations planned for January 2027.

VietVance

1 min read

BIWASE’s waste-to-energy plant in Ho Chi Minh City is entering the final stage of construction. Work began on June 26, 2025, with total investment of about VND 1.15 trillion. The project is planned to have 24 MW of generating capacity, including 12 MW in its first phase, which is expected to process about 500 tonnes of waste a day. According to information released on November 18, 2026, the first-phase generating unit is scheduled to begin operations in January 2027.

By mid-November 2026, several major components of the plant were 95% to 100% complete. The turbine building and its enclosing structure were 98% complete, while installation of the turbine, gearbox and generator was about 95% complete. Installation of incinerator equipment was 87% complete, and the furnace casing and oxygen supply fans were 95% complete. All major equipment for the incinerator, boiler and turbine building had arrived at the site.

To advance construction, the site at one point had nearly 500 engineers and workers from about 14 contractors working simultaneously on civil works, equipment installation, power generation systems and environmental protection facilities. BIWASE previously put a 5 MW waste-to-energy plant into operation on January 12, 2024. The new project’s first phase has 2.4 times that plant’s generating capacity.

Other waste-to-energy projects in Vietnam have varied in construction time and scale. A Hanoi project designed to process 4,000 tonnes of waste a day began construction in August 2019 and started accepting waste about 33 months later. Another project designed to process 2,250 tonnes a day began construction on March 30, 2022, and started accepting and processing waste on May 1, 2025. A waste-to-energy plant in Can Tho began construction on June 30, 2017, and started accepting waste for trial operations about 15.5 months later. These projects have different processing capacities from BIWASE’s first phase.

Source: VietVance