Vietnam’s Núi Vung Tunnel Plans to Open Second Tube in 2027
Vietnam’s Núi Vung Tunnel faced falling rock and dangerous ground movement on Lunar New Year’s Eve in 2022. After reinforcement, the tunnel was connected in July 2023. A project to complete its second tube was approved in 2025, with completion planned for 2026 and operation from 2027.
The Núi Vung Tunnel on the Cam Lâm–Vĩnh Hảo Expressway is about 2.2 km long, and the original project cost approximately VND 1.6 trillion. On Lunar New Year’s Eve in 2022, Ngô Hữu Khoa, then executive manager of the tunnel project, noticed small rocks falling from the tunnel crown while inspecting the excavation face. Two of eight monitoring points subsequently showed movement at dangerous levels. Crews sprayed concrete through the night and added rock bolts and other supports until the readings stabilized.

Falling rock and dangerous movement at monitoring points occurred during construction of the Núi Vung Tunnel.(VietVance)
Built using the New Austrian Tunneling Method, the tunnel encountered a weak geological zone and strong groundwater flow after about 300 meters of excavation, causing cracks in the sprayed concrete. The builders addressed the danger through drainage, grouting, more closely spaced steel arches and additional support structures. Geological problems affected progress: as of March 28, 2023, 1,915 meters of the left tube and about 1,610 meters of the right tube had been excavated, against a planned excavation length of 2,250 meters for each.
The builders then moved equipment and workers to the three remaining excavation faces and introduced three shifts a day. On July 3, 2023, the excavation faces advancing from the tunnel’s north and south ends met. The tunnel was developed by Công ty CP BOT Cam Lâm – Vĩnh Hảo and Tập đoàn Đèo Cả. It lies on the 78.5 km Cam Lâm–Vĩnh Hảo Expressway, which was financed under a BOT arrangement.

The Núi Vung Tunnel was connected on July 3, 2023.(VietVance)
The first phase completed one tube for traffic in both directions. The other tube has been excavated, reinforced and lined. A project to complete the second tube was approved in 2025. Its route is about 5.4 km long, including 2.287 km of tunnel, with a preliminary total investment of more than VND 1.16 trillion. The project is scheduled for completion in 2026 and operation from 2027.
Tập đoàn Đèo Cả participated in the tunnel’s construction. At an analyst meeting on October 12, 2026, the related listed company Công ty CP Đầu tư Hạ tầng Giao thông Đèo Cả (HHV) reported estimated consolidated revenue of about VND 2.978 trillion for the first nine months of 2026, up 15% year on year. Consolidated after-tax profit was VND 564 billion, up 18%. The total value of new construction contracts signed during the same period exceeded VND 5.3 trillion.
Source: VietVance