Construction advances on Dong Nai’s ĐT769 road, with 6 km eight-lane section taking shape

Dong Nai’s ĐT769 road upgrade and expansion began in July 2026. A roughly 6 km section linking areas around Long Thanh Airport has largely completed site leveling and roadbed filling. Work is under way at six sites, while about 82 hectares of land, or roughly 60% of the total required, has been handed over.

VietVance

1 min read

Construction is advancing on the upgrade and expansion of Dong Nai’s ĐT769 road. A newly built section of about 6 km through a rubber plantation, designed for eight lanes, has largely completed site leveling and roadbed filling and is taking shape. The project is one of the key transport works connecting areas around Long Thanh Airport.

The newly built section of about 6 km through a rubber plantation is designed for eight lanes.(VietVance)

The new road runs from near a cemetery in Bình An to the Lộc An–Bình Sơn resettlement area. Dong Nai Rubber Company handed over the land for this section early, enabling roadbed construction. Materials are also being assembled, machinery mobilized and sites cleared along other sections of the project.

The Dong Nai City Transport Construction Investment Project Management Board said work is under way at six sites. Activities include clearing surface vegetation and soil, filling the roadbed, building drainage systems and testing piles for a railway overpass. About 82 hectares of land have been handed over, roughly 60% of the more than 135 hectares required; land acquisition and clearance continue on the remaining plots.

Roadbed, drainage and bridge-related construction is advancing at multiple sites along ĐT769.(VietVance)

About 82 hectares of land have been handed over for the project, roughly 60% of the total area required.(VietVance)

The project management board has urged local authorities along the route to hand over land in priority construction areas soon, so that roadbed fill can be moved and bridges built. ĐT769 runs from National Highway 1 to National Highway 51 and has a total investment of about VND 2.796 trillion. Construction began in July 2026 and is scheduled for completion in January 2028.

Source: VietVance