Dung Quất refinery expansion advances as EPC bid comes in below budget

The Dung Quất refinery expansion is scheduled for trial operation by the end of 2028. PSI says the EPC bid was about $1 billion, roughly $200 million below the approved tender budget, but actual savings can only be determined after the project is completed and its accounts are settled.

VietVance

2 min read

An analysis report released on November 18 by Petroleum Securities Company (PSI) says the Dung Quất refinery upgrade and expansion project, undertaken by Vietnam Refining and Petrochemical Corporation (BSR), is scheduled for trial operation by the end of 2028. The project signed an engineering, procurement and construction (EPC) contract on July 9, 2026, and work now focuses on technical design, procurement of equipment with long lead times, and preparations to connect the expansion to the existing refinery.

The Dung Quất refinery upgrade and expansion project.(VietVance)

The EPC contractor is a consortium of China Chengda Engineering and Beijing Petrochemical Engineering. The parties held a project kickoff meeting on August 21, 2026. By the end of September, the contractor had completed preliminary work, including a site survey. PSI says more than 85% of site leveling is complete, and the site is expected to be handed over to the EPC contractor in November 2026.

PSI says the winning EPC bid was about $1 billion, 17% below the approved tender budget of $1.2 billion, a difference of roughly $200 million. The lower bid is expected to reduce investment cost per unit of capacity, but PSI cautions that actual savings can only be determined after the project is completed and its accounts are settled. BSR is considering raising its equity contribution to about 70% of total project investment, with the remainder financed through commercial loans and export credit. It plans to complete the financing arrangements in the second quarter of 2027.

The Dung Quất refinery upgrade and expansion project.(VietVance)

The refinery plans to undergo its sixth major maintenance shutdown in July 2027, with operations halted for up to 32 days. Connection work for the expansion is expected to begin on July 1 and last 21 days. PSI expects the maintenance to affect BSR’s output and profit in the third quarter of that year. Located in the Dung Quất Economic Zone in Quảng Ngãi Province, the refinery currently has a design capacity of 6.5 million tonnes of crude oil a year. Capacity is expected to rise to 8.5 million tonnes a year after the expansion is completed.