Gemalink Deepwater Port Expansion to Raise Annual Capacity Above 3 Million TEU
Gemalink Deepwater Port broke ground on its second phase in April 2026. The project includes a berth for 250,000 DWT vessels and an investment of about VND 8.361 trillion. Once complete, the port’s annual capacity will exceed 3 million TEU. Its soft ground has required extensive piling and drainage-based soil consolidation.
Gemalink Deepwater Port in the Cái Mép Hạ area of Ho Chi Minh City held a groundbreaking ceremony for its second phase in April 2026. The phase is planned to add a 285-meter main berth, a 359-meter upstream berth and a 390-meter barge berth, accommodating vessels or barges of 250,000, 150,000 and 5,661 DWT, respectively. Investment is estimated at VND 8.361 trillion. Once the project is complete, the port’s annual handling capacity will exceed 3 million TEU.

Image related to the Gemalink Deepwater Port project.(VietVance)
The port site was formerly part of Bà Rịa–Vũng Tàu Province. The project’s planned main berths total 1,150 meters in length, and its land and water areas cover 93 hectares. Phase one has brought 800 meters of main berth and 190 meters of other berths into service and can accommodate vessels of up to 232,000 DWT. The project’s investor, Gemalink, is a joint venture between Gemadept Group and France’s CMA CGM; Gemadept holds 50% of its voting rights and a 65.13% economic interest.
Much of the port area consists of tidal flats with thick layers of soft soil. According to the Vietnamese Geotechnical Association, contractors drove 1,217 prestressed concrete pipe piles measuring 52 to 66 meters and 221 inclined steel piles measuring 54 to 70 meters for the berths. The container yard behind them was treated using preloading and prefabricated vertical drains, with vacuum consolidation also used in some areas. Monitoring data published by the association show that consolidation settlement during treatment reached up to 6 meters.
Gemalink began operations in January 2021. According to figures released by Gemadept, the port handled 2,018 vessel calls and 6.5 million TEU of cargo from 2021 to 2025. CMA CGM said in April 2026 that the port was then handling about 1.7 million TEU a year and operating at full capacity.

Image related to operations at Gemalink Deepwater Port.(VietVance)
A report by ACB Securities showed that Gemalink’s container throughput rose about 23% year on year in the first half of 2026, while profit increased 67% to VND 532 billion. Gemadept reported third-quarter 2026 net revenue of VND 2.21 trillion, up 42% year on year; pretax profit for the first three quarters rose 68% to VND 2.977 trillion.