More Than 17 km of Elevated Ring Road in Ho Chi Minh City Nears Completion

The elevated section of Ho Chi Minh City's Ring Road 3 is expected to have its main carriageway and connections at both ends completed before November 30. It will provide another route toward Long Thành Airport, although an official opening date has not been set.

VietVance

2 min read

The more than 17 km section of Ho Chi Minh City's Ring Road 3 through the former Thủ Đức City is expected to have its elevated main carriageway and connections at both ends completed before November 30, 2026. On November 23, crews were still finishing work between the Tân Vạn and Long Trường interchanges. The section consists mainly of viaducts, with four lanes carrying traffic in both directions and a design speed of 100 km/h. It is Ho Chi Minh City's first large-scale elevated road.

The main viaduct structure is largely complete. The section through the Vinhomes Grand Park urban area has been paved with asphalt and marked with lane lines, while barriers, guardrails and noise walls have been installed. The remaining work is concentrated mainly at the Tân Vạn and Long Trường interchanges.

Tạ Xuân Liêm, general director of Công ty TNHH Tập đoàn Ruby, one of the main contractors, said major works at the Long Trường interchange were largely complete. About 120 engineers and workers are laying asphalt and installing traffic safety equipment and lighting; the remaining work is expected to be finished in November. The interchange has six ramps connecting the elevated ring road with the Ho Chi Minh City–Long Thành–Dầu Giây Expressway and the approach to the Nhơn Trạch Bridge, which is already in use.

Work is also being accelerated at the Tân Vạn interchange so it can be completed alongside the elevated section. The Ho Chi Minh City Management Board for Traffic Works Construction Investment Projects, the project owner, said the goal was to complete the elevated main carriageway and connections at both interchanges before November 30. An official opening date has yet to be set: the project still requires evaluation, acceptance and approval of its traffic management plan. The service roads on both sides are expected to be completed by year-end because of shortages of stone and asphalt.

Map of the Ring Road 3 route.(VietVance)

Ring Road 3 extends more than 90 km through Ho Chi Minh City, Đồng Nai and Tây Ninh. The elevated section is part of a more than 76 km first-phase project being funded by local governments, with total investment of nearly VND 75.4 trillion. Once in use, it will provide another transport link between northern and eastern Ho Chi Minh City and Đồng Nai, as well as a new route to Long Thành Airport.