Hòa Phát’s Six Blast Furnaces in Operation as Monthly Molten Iron Output Reaches 1 Million Tonnes

Hòa Phát’s Dung Quất steel complex produced 1 million tonnes of molten iron in August 2026, up nearly 65% year on year. All six blast furnaces are operational, including two large furnaces built for the Dung Quất 2 project. As output rose, the group’s third-quarter revenue and after-tax profit also increased year on year.

VietVance

2 min read

Hòa Phát Group announced that its Dung Quất steel complex produced 1 million tonnes of molten iron in August 2026, up about 2% from July and nearly 65% from a year earlier. The complex currently operates six blast furnaces: four with a capacity of 1,080 cubic meters each in the first phase and two with a capacity of 2,500 cubic meters each in the second phase.

The sixth blast furnace was fired up in early September 2025. It is the second blast furnace in the Dung Quất 2 project. Contractor Danieli Corus said the furnace produced its first molten iron on the day it was fired up and, after a short ramp-up, stabilized at 7,500 tonnes of molten iron per day. According to the contractor, it took eight years from the signing of the first contract to complete and commission all six blast furnaces.

All six blast furnaces use Danieli Corus’s cooling and lining design. Copper cooling plates work with highly conductive graphite refractory bricks to form a protective layer on the furnace lining. The contractor said blast furnaces must operate continuously under high temperatures and pressure. To produce molten iron at a lower cost, the continuous operating period between major overhauls must exceed 20 years. This is the operating period the design aims to achieve, not the number of years the six furnaces have already been running.

Image related to the six blast furnaces at Hòa Phát Group’s Dung Quất steel complex.(VietVance)

The contract for the four first-phase blast furnaces was signed in 2017. The first furnace was blown in on June 29, 2019, and the fourth began operating in 2021. The contract for the two large second-phase furnaces was signed in December 2021. The fifth furnace was fired up in December 2024, and the sixth produced molten iron in September 2025. Danieli Corus data show that, with all six furnaces operating, the Dung Quất complex has annual steel production capacity of about 10 million tonnes. The second-phase project has an investment of VND 85 trillion and is designed to produce 5.6 million tonnes of hot-rolled coil a year.

Image related to the blast furnace project at Hòa Phát Group’s Dung Quất steel complex.(VietVance)

In the third quarter of 2026, Hòa Phát Group produced 3.7 million tonnes of crude steel, up 85% year on year. Revenue was VND 6.2669 trillion, up 70%, and after-tax profit was VND 826.5 billion, up 106%. The group said profit growth was linked to higher crude steel sales volumes and generally favorable costs and selling prices. In the first nine months, group revenue was VND 17.1539 trillion and after-tax profit was VND 2.3746 trillion, up 54% and 104% year on year, respectively.

Source: VietVance