Second tube of Núi Vung tunnel planned to open in 2027
Vietnam approved the Núi Vung tunnel completion project in 2025, with construction scheduled to finish in 2026 and operations to begin in 2027. The tunnel faced weak ground and a risk of collapse during construction before its excavation fronts met in July 2023. A company involved in the project also reported operating figures for the first nine months of 2026.
The Núi Vung tunnel is on the Cam Lâm–Vĩnh Hảo Expressway. Its completion project was approved in 2025 and covers a route of approximately 5.4 kilometers, including 2.287 kilometers of tunnel and 3.093 kilometers of bridges and approach roads. Preliminary total investment exceeds VND 1.16 trillion. The project is scheduled for completion in 2026 and to enter service in 2027. One previously completed tube carries two-way traffic on two lanes, while the other is being completed.
Construction of the tunnel encountered a dangerous incident. On Lunar New Year's Eve in 2022, Ngô Hữu Khoa, then the project's executive manager, spotted small rocks falling from the tunnel crown near the excavation face. Monitoring showed that displacement at two of eight measurement points had reached dangerous levels. The construction team immediately mobilized equipment, sprayed concrete through the night, installed additional anchors and applied more sprayed concrete where the layer was too thin.

Image related to construction of the Núi Vung tunnel.(VietVance)
After excavation had advanced about 300 meters, the tunnel face also encountered weak ground and a strong flow of groundwater, and the sprayed concrete began to crack. The project team addressed the danger through drainage, grouting and additional support structures. By March 28, 2023, the left and right tubes had been excavated to 1,915 meters and approximately 1,610 meters, respectively, both short of their design length of 2,250 meters. The excavation fronts from the two ends finally met on July 3, 2023.

Image related to construction of the Núi Vung tunnel.(VietVance)
The project was carried out by Công ty CP BOT Cam Lâm – Vĩnh Hảo and Tập đoàn Đèo Cả. On October 12, 2026, Công ty CP Đầu tư Hạ tầng Giao thông Đèo Cả (HHV) announced that estimated consolidated revenue for the first nine months of the year was approximately VND 2.978 trillion, up 15% year on year; consolidated after-tax profit was VND 564 billion, up 18%. The total value of new construction contracts signed during the same period exceeded VND 5.3 trillion.