Khánh Hòa urges faster land clearance for two Ninh Thuận nuclear power projects
On November 16, 2026, a Khánh Hòa provincial team inspected progress on two Ninh Thuận nuclear power projects. Land clearance for Ninh Thuận 1 has fallen short of an earlier target, while Ninh Thuận 2 faces overlapping forest land claims, compensation disputes and a shortage of fill material. Provincial authorities called for faster construction of resettlement areas and the handover of project land.
On the afternoon of November 16, 2026, a Khánh Hòa Provincial People's Committee delegation inspected progress on work related to the Ninh Thuận 1 and 2 nuclear power plant projects. Provincial Vice Chairman Trịnh Minh Hoàng called on local authorities and the project owner to resolve land clearance obstacles more quickly and advance construction of resettlement areas to make land available for the projects.
The Ninh Thuận 1 project is in Phước Dinh commune. The commune had pledged to complete more than 85% of land clearance by the end of October 2026 but has yet to meet that target. The users and origins of use of some land still need to be verified. The resettlement area is under construction, and no plots are yet available to allocate to households being relocated. Although some compensation and resettlement plans have been approved, local authorities are still unable to issue land recovery decisions on that basis.
The Ninh Thuận 2 project is in Vĩnh Hải commune. Local authorities found that 47 land plots covering about 9.9 hectares overlap with forest land managed by Núi Chúa National Park. People associated with another 37 plots in the plant area have not agreed to accept compensation, while those associated with four plots in the resettlement area have refused compensation and filed complaints. A supporting component of the project also lacks fill material: of the approximately 461,000 cubic meters required by the design, about 231,000 cubic meters must come from outside sources, but the proposed extraction site has yet to receive approval from the competent authority.
Trịnh Minh Hoàng directed Phước Dinh commune to clarify how much land has been recovered and the status of efforts to identify land users, draw up a completion plan, and hand over the project land to the project owner by November 30, 2026. He also instructed Vĩnh Hải commune to propose a plan for resolving the overlap with forest land. As the owner of the related works, the provincial Construction Investment Project Management Board must coordinate with local authorities to resolve outstanding issues and speed up construction of the resettlement areas.