Some Phase 1 Works at Long Thanh Airport Expected to Extend to June 2027

Component Project 3 of Phase 1 of Long Thanh International Airport cannot be completed in 2026 under its contractual schedule. Some major works are expected to be completed or finish trial runs by June 2027. The Vietnamese government has directed the investor to review construction and contract issues, propose lawful solutions and clarify when the airport can begin operations.

VietVance

2 min read

On November 25, Vietnam’s Standing Deputy Prime Minister Phạm Gia Túc chaired a meeting and called for faster resolution of construction obstacles affecting Phase 1 of Long Thanh International Airport. He also called for existing problems to be handled in accordance with the law, without legitimizing violations or allowing new ones. The project investor, Airports Corporation of Vietnam (ACV), said Component Project 3 could not be completed in full in 2026 under its contractual schedule.

Meeting to address construction issues affecting Phase 1 of Long Thanh International Airport.(VietVance)

ACV said the value of work completed on Component Project 3 had reached VND 76,953.8 hundred million, equivalent to 88.63% of the contract value; disbursements had reached VND 49,507.3 hundred million, or 57% of the contract value. Major works, including the passenger terminal, Cargo Terminal No. 1, parking building and airport management system, are expected to be completed or finish trial runs by June 2027.

ACV identified three main types of obstacle: some materials and equipment were purchased and installed from manufacturers or to specifications different from those in the contracts before the investor approved the changes and the contracts were amended; some works were built and accepted under approved construction drawings that did not match the approved technical designs; and other works began before their construction drawings were approved. ACV said resolving these issues was necessary for final acceptance of the works and for the airport to obtain an operating permit.

Vietnam’s Standing Deputy Prime Minister Phạm Gia Túc speaks at the meeting.(VietVance)

The meeting directed ACV to review changes, construction quality and payment issues item by item, and to set clear dates for the remaining construction, equipment installation, trial runs and start of operations. ACV must report to the government within one week of the meeting on why the project cannot be completed in 2026. The Ministry of Construction must report on project progress by December 10, 2026, and compile the relevant agencies’ views on how to address the issues by December 15. The airport may begin operations only after the works have passed final acceptance and aviation licensing procedures have been completed. Ho Chi Minh City and Dong Nai Province must also advance transport links to the airport and supporting facilities for its operation.