Long Thanh Airport’s First Phase Cannot Be Completed in 2026
Airports Corporation of Vietnam says Component 3 of Long Thanh International Airport’s first phase cannot be completed in 2026 under the contractual schedule. Several major works are expected to be completed or finish trial runs in June 2027. The government has called for a review of the remaining work and legal obstacles and will consider adjusting the project timeline.
Vietnam’s Standing Deputy Prime Minister Phạm Gia Túc chaired a meeting on November 25 to address problems affecting construction of the first phase of Long Thanh International Airport. Airports Corporation of Vietnam (ACV) reported that work completed on Component 3 was valued at VND 76.9538 trillion, equivalent to 88.63% of the contract value; disbursements reached VND 49.5073 trillion, equivalent to 57% of the contract value.

A meeting to address problems affecting construction of the first phase of Long Thanh International Airport.(VietVance)
ACV said that, because of both objective and subjective factors, Component 3 cannot be completed in full in 2026 under the contractual schedule. Major works including the passenger terminal, Cargo Terminal No. 1, the parking facility and the airport management system are expected to be completed or finish trial runs in June 2027. ACV proposed that the Ministry of Construction conduct a comprehensive review of progress across the project components and ask the competent authorities to consider adjusting the implementation period for the first phase.
The obstacles identified by ACV include materials and equipment whose manufacturers, brands, types or places of origin differ from those specified in the contracts, with orders or installation proceeding before the changes were approved and contract addenda signed. Some works were built and accepted according to approved construction drawings that did not match the approved technical design. Other works began before their construction drawings were approved. ACV said resolving these issues is necessary for final acceptance of the works and for the airport to obtain an operating permit.

Vietnam’s Standing Deputy Prime Minister Phạm Gia Túc speaks at the meeting.(VietVance)
Phạm Gia Túc called for outstanding issues to be handled in accordance with the law, without legitimizing violations or allowing new ones to arise. ACV must set out milestones for the remaining construction work, equipment installation and trial operations, as well as when the project could enter service, and report to the government within one week of the meeting, copying the Ministry of Construction. The ministry must report on project progress by December 10, 2026, and compile the issues and proposed solutions for submission to the government and prime minister by December 15.
ACV must also ensure that contractors have the funds needed to continue construction and assess the quality and suitability of the equipment concerned. The airport may enter service only after the works have passed final acceptance, operating conditions have been inspected and aviation licensing procedures have been completed. Ho Chi Minh City and Dong Nai province will continue developing transport links to the airport and ensure the conditions needed to supply fuel for airport operations.