Vietnam-Built Offshore Wind Substation Energized off Taiwan
PTSC M&C built the jacket and topside for the Fengmiao 1 offshore wind substation in Vung Tau. The structures were installed off Taiwan in August 2026, and the substation was energized in October. The 495 MW wind farm is expected to connect to the grid by the end of 2027.
The substation for the Fengmiao 1 offshore wind project was energized in October 2026. Its jacket and associated piles, weighing more than 8,000 tonnes in total, were built in Vung Tau by Vietnamese company Công ty TNHH MTV Dịch vụ Cơ khí Hàng hải PTSC (PTSC M&C). The 3,400-tonne topside was also built there. Both structures were transported to waters off Taiwan and installed in August.

The jacket and associated piles for the Fengmiao 1 offshore substation, built by PTSC M&C in Vung Tau, left the fabrication yard in April 2026.(VietVance)
Fengmiao 1 is located about 36 kilometers from Taichung, off Taiwan’s west coast. It has a planned capacity of 495 MW, with 33 turbines rated at 15 MW each. The project is owned by Danish infrastructure investment fund Copenhagen Infrastructure Partners. In 2023, a consortium of PTSC M&C and Danish company Semco Maritime won the contract to design, procure and construct the substation. The substation will collect power from the turbines and transmit it to shore through subsea cables.
PTSC M&C completed the jacket and loaded it onto a barge on April 22, 2026. The associated piles had left the fabrication yard 11 days earlier. The company said the two structures were completed one month ahead of the planned 11-month schedule. The 3,400-tonne topside left the fabrication yard in late July. At the jacket’s departure ceremony, project manager Đặng Minh Hải said it was, at the time, the world’s deepest-water offshore substation jacket used for high-voltage alternating-current transmission.

The topside of the Fengmiao 1 offshore substation left the fabrication yard in late July 2026.(VietVance)
Installation of the turbine foundations continued after the substation was energized. Offshore Wind reported on November 13, 2026, that Fengmiao 1’s transmission system was fully operational; the project owner expects the wind farm to connect to the grid by the end of 2027. On the same day, PTSC M&C and Semco Maritime signed a contract to design, procure and construct the offshore substation for the 600 MW Fengmiao 2 project. PTSC reported net revenue of VND 27.852 trillion for the first three quarters of 2026, up 21% year on year, and after-tax profit of VND 1.344 trillion, up 42%.