Three Mountain Tunnels Advance in Phase 2 of Northeastern Vietnam Expressway

Work is advancing on three mountain tunnels in phase 2 of the Đồng Đăng–Trà Lĩnh Expressway. The south portal of the left bore of Tunnel 3A opened on November 12, 2026, and contractors aim to break through the bore by the end of February 2027. The expressway will extend more than 121 kilometers and has a total investment of VND 26.184 trillion.

VietVance

2 min read

The south portal of the left bore of Tunnel 3A on phase 2 of Vietnam’s Đồng Đăng–Trà Lĩnh Expressway opened on November 12, 2026. Located on the boundary between Quảng Uyên and Trà Lĩnh in Cao Bằng Province, the tunnel has a 468-meter left bore and a 395-meter right bore. It has the most difficult construction conditions of the three mountain tunnels in phase 2.

Construction crews work at the south portal of Tunnel 3A’s left bore.(VietVance)

Nguyễn Bá Triều, deputy director of the phase 2 project management board, said construction conditions are difficult at both ends of Tunnel 3A. The south portal is close to a residential area, complicating land clearance and blasting; at the north portal, the access road must overcome an elevation difference of about 40 meters from the natural terrain. Contractors plan to break through the left bore by the end of February 2027 and aim to break through the right bore around April 30, 2027. Of the other two phase 2 tunnels, both bores of Tunnel 4 have been completed; portal construction on Tunnel 3 began in late October 2026, and the tunnel is expected to be completed in July 2027.

The expressway passes through Cao Bằng and Lạng Sơn provinces. It will extend more than 121 kilometers and has a total investment of VND 26.184 trillion. Phase 1 began on January 1, 2024, with construction of a 93.35-kilometer section. Phase 2 began on August 19, 2025, and is set to widen the phase 1 section and build a new 27-kilometer stretch to the Trà Lĩnh border crossing. Once completed, the project is expected to connect Hanoi and the Red River Delta with the mountainous northeast of Vietnam and form a freight corridor with neighboring expressways.

Đèo Cả Group, the lead company in the investment consortium, said the right bore of the phase 1 Đông Khê Tunnel broke through on November 26, 2024. It was the first tunnel bore completed along the expressway, three months ahead of schedule. Construction work inside and outside the two phase 1 mountain tunnels, Đông Khê and Thất Khê, is now largely complete.

Source: VietVance