Cam Lộ–La Sơn Expressway Expansion May Be Delayed Until 2027
Construction on Vietnam’s Cam Lộ–La Sơn expressway expansion has reached nearly 49% of the contract value. The project management board plans to seek approval to delay its opening from 2026 to 2027 and reduce total investment by nearly VND 723 billion. Delayed land handover, prolonged rain and asphalt shortages have slowed work.
On November 22, the Ho Chi Minh Road Project Management Board said it planned to submit a revised schedule for the Cam Lộ–La Sơn expressway expansion to the Ministry of Construction, seeking to postpone its planned 2026 opening until 2027. The project runs through Quảng Trị and Huế, and completed construction work amounts to nearly 49% of the contract value. The project management board also proposed reducing total investment by nearly VND 723 billion to more than VND 5.74 trillion and reallocating the funding plan.

The management board for the Cam Lộ–La Sơn expressway expansion is seeking to postpone completion until 2027.(VietVance)
The project spans nearly 99 kilometers and will widen the road from two lanes to four while completing bridges, interchanges, an automatic toll collection system and rest stops. Work on the two main construction packages, XL1 and XL2, did not begin until December 19, 2025, and the contract for package TB1 was signed on October 21, 2026. The project management board still aims to complete XL1, for which the construction site has largely been handed over, in 2026, but considers it difficult to finish the other three packages within the year. There are currently 108 construction fronts and more than 1,000 workers along the route.
Land handover and weather have affected progress. Land for the National Highway 15D interchange in Quảng Trị was handed over on November 2; more than four hectares remain unresolved in Huế, including areas at the Provincial Road 12B interchange. The filled roadbed on soft ground at that interchange also needs time to settle. Rain since early September has slowed work on the roadbed, pavement and drainage system, while an asphalt shortage in October interrupted asphalt concrete work. The project management board said the price of 60/70-grade asphalt at a warehouse in Đà Nẵng rose from VND 16,800 per kilogram in March to VND 26,400 in November.

The project management board believes the war in the Middle East has driven up asphalt prices and is one reason the project’s progress has been affected.(VietVance)
Traffic must continue to use the road during construction, requiring contractors to work lane by lane and section by section. The project management board acknowledged that some contractors were slow to mobilize personnel, equipment and materials, while it had sometimes failed to reassign work promptly from contractors behind schedule. During an inspection of the project on July 9, 2026, Minister of Construction Trần Hồng Minh called for faster work, aiming to complete the project by November 30 and hand it over by the end of December.
Source: VietVance