North–South High-Speed Railway Through Dak Lak: About 3,000 Households Need Resettlement

The North–South high-speed railway will run nearly 99 kilometers through Dak Lak province and is expected to occupy more than 800 hectares. It will affect more than 5,500 houses and land plots, while about 3,000 households will need resettlement. The province is advancing resettlement planning and has requested central budget funding for 2026.

VietVance

1 min read

On the afternoon of November 16, Dak Lak province held a meeting on land acquisition for the provincial section of the North–South high-speed railway project. According to a report presented at the meeting, the route will run nearly 99 kilometers through the province, crossing 13 communes and wards. It is expected to occupy more than 800 hectares, with one passenger station and two maintenance facilities planned along the route. A preliminary review found that the project will affect more than 5,500 houses and land plots, as well as six organizations, and that about 3,000 households will need resettlement.

Representatives of Dak Lak provincial departments report on the project's progress at the November 16 meeting.(VietVance)

Of the 23 planned resettlement and reburial sites, 20 have had their 1:500 detailed plans approved or their overall site plans accepted by commune-level People's Committees. These comprise 15 resettlement areas and five reburial areas. Planning procedures are still underway for the remaining three resettlement areas. One is expected to receive approval on November 17, while procedures for the other two are expected to be completed before November 25.

Dak Lak province has registered a need for 385 billion Vietnamese dong in central budget funding for 2026, comprising 360 billion dong for resettlement areas and 25 billion dong for reburial areas. It has asked the Ministry of Construction and the Ministry of Finance to consider allocating the funds.

Dak Lak provincial Party secretary Lương Nguyễn Minh Triết called on relevant departments, local authorities and the project developer to expedite investment, planning, land and environmental procedures and prepare compensation and land acquisition plans in advance. He called for construction to begin simultaneously in 2026 on the 20 resettlement areas whose plans have been approved, with infrastructure at least as good as in residents' former neighborhoods.