Hanoi underpass completion proposed for Q2 2028
Hanoi’s construction department has proposed extending the deadline for the Hoàng Quốc Việt–Phạm Văn Đồng underpass project from the second quarter of 2027 to the end of the second quarter of 2028, citing land clearance delays and a construction tender that attracted no bidders.
Hanoi’s construction department has asked the city government to consider extending the implementation deadline for Subproject 2, which covers an underpass at the intersection of the extended Hoàng Quốc Việt Road and Phạm Văn Đồng Road and a connection to Trần Vỹ Street, to the end of the second quarter of 2028. The previously approved plan called for completion in the second quarter of 2027; the proposed extension is still awaiting approval.

Rendering of the Hoàng Quốc Việt Road underpass beneath Ring Road 3.(VietVance)
Võ Nguyên Phong, head of Hanoi’s construction department, said land clearance and the selection of a construction contractor had encountered obstacles. After tender documents for construction package 01/XL were issued online, no contractors submitted bids, requiring the project schedule to be adjusted to accommodate the package’s next steps.
Subproject 2 is funded by Hanoi’s budget, with a total investment of more than VND 1.106 trillion. The project owner is the Hanoi Traffic Infrastructure Construction Investment Project Management Board. The route is approximately 1.203 kilometers long, including 672.8 meters of tunnel and retaining walls, and the underpass will have six lanes. The project also includes extending Hoàng Quốc Việt Road to Trần Vỹ Street, as well as a drainage pumping station, lighting and traffic signals.
Compensation and land clearance for agricultural land under Subprojects 1.1 and 1.2 are largely complete, covering approximately 30,500 and 36,646 square meters, respectively. Underground and aboveground utilities are still being relocated, and all land clearance is expected to be completed in the second quarter of 2027. Hanoi’s construction department said the proposed new deadline aligns with land clearance progress. It also asked the project owner and relevant local authorities to establish the reasons for the delay, promptly hold a new tender and draw up specific schedules for each part of the work.
Source: VietVance