Nearly 10 km of Ho Chi Minh City–Long Thanh Expressway Expanded to 10 Lanes
VEC said on November 19 that nearly 10 km of expanded roadway on the Dong Nai section of the Ho Chi Minh City–Long Thanh Expressway is ready for use. Traffic is scheduled to shift onto it from midnight on November 22, 2026, so the existing roadway can be upgraded. Other sections and the new Long Thanh Bridge remain under construction.
Vietnam Expressway Development and Investment Corporation (VEC) said on November 19 that nearly 10 km of expanded roadway on the Ho Chi Minh City–Long Thanh Expressway, from just beyond the approach to Long Thanh Bridge to the National Highway 51 interchange, has been completed and is ready for use. Traffic is scheduled to shift onto the new roadway from midnight on November 22, 2026, allowing contractors to upgrade the existing roadway. Temporary signs and road markings have been installed to guide drivers.

In November 2026, contractors built expanded roadway along both sides of the expressway in Dong Nai in preparation for its opening.(VietVance)
This section is part of the expansion project’s second construction package. The package extends nearly 12 km to the Bien Hoa–Vung Tau Expressway interchange and is designed to increase the number of lanes from four to 10. Nearly 82% of the work has been completed. Construction continues on the remaining section from the National Highway 51 interchange to the Bien Hoa–Vung Tau Expressway, with completion expected in December 2026.

Diagram of the expanded section of the Ho Chi Minh City–Long Thanh Expressway.(VietVance)
On the Ho Chi Minh City side, the first construction package covers nearly 10 km, from the Ring Road 2 interchange to Ring Road 3 and the Long Thanh Bridge area. It is planned to expand from four to eight lanes, and more than 81% of the work has been completed. A new bridge nearly 24 meters wide, with five lanes, will also be built to the right of the existing Long Thanh Bridge when traveling from Ho Chi Minh City toward Dong Nai. VEC expects the package’s viaduct works to be substantially completed in December 2026 and opened to traffic in January 2027. The new Long Thanh Bridge is expected to be completed in the first quarter of 2027.
The expansion project began in August 2025. It spans nearly 22 km and has a total investment of VND 14.945 trillion, funded by the state budget and capital raised by VEC. The route is planned to expand to eight to 10 lanes, except in the Long Thanh Bridge area. The Ho Chi Minh City–Long Thanh–Dau Giay Expressway is about 55 km long and has been in operation for more than 10 years. It frequently experiences congestion on weekends and holidays. The expansion is expected to ease traffic pressure at Ho Chi Minh City’s eastern gateway.