Vietnam’s Ô Môn 3 Power Plant Secures ¥27.901 Billion Japanese Loan

The Japan International Cooperation Agency signed an agreement on November 9, 2026, to lend up to ¥27.901 billion to the Ô Môn 3 gas-fired power plant in Cần Thơ. An exchange of notes signed in 2013 places the project outside Japanese financing restrictions introduced at the end of 2022. The plant is expected to begin commercial operations in May 2030.

VietVance

1 min read

The Japan International Cooperation Agency (JICA) signed an agreement in Tokyo on November 9, 2026, to provide an official development assistance loan of up to ¥27.901 billion for the Ô Môn 3 combined-cycle power plant in Cần Thơ, Vietnam. The annual interest rate is 1.4% for construction and 0.01% for consulting services; the loan has a 30-year term, including a 10-year grace period.

A policy added by the Japanese government in June 2022 provides that, in principle, it would cease new direct public support for overseas fossil fuel projects without emissions reduction measures from the end of that year, subject to limited exceptions. JICA said Ô Môn 3 is outside the scope of that restriction because the two governments signed an exchange of notes on the project loan on March 22, 2013.

JICA estimates the project’s total investment at about ¥197.031 billion. The new loan accounts for 14.2%, with the remainder expected to come from sources including the developer’s own funds and commercial loans. The project is being developed by the Vietnam National Industry and Energy Group (Petrovietnam). Information released by Mitsubishi Power on November 19, 2026, shows that the plant’s design capacity is 1,155 MW, about 54% higher than the 750 MW proposed in 2012.

The project was originally scheduled to begin commercial operations in November 2016. JICA now expects it to start operating in May 2030 and has set a target of about 6.12 billion kWh of electricity supplied annually by 2032. JICA said the plant’s operating performance depends on progress in developing the Lô B gas field; construction of the field and related pipelines has begun, with gas supply planned from 2027.

Source: VietVance