Seven Red River Bridge Projects Advance Amid Land Handover and Supply Challenges
Construction is underway on seven bridges across the Red River, but some work sites remain affected by land handover, utility relocation, and shortages of materials and labor. Tứ Liên Bridge has received all land within its acquisition area, though some sites are not yet ready for construction. Contract work on the Ngọc Hồi and Trần Hưng Đạo bridges is about 27% and 48% complete, respectively.
Seven bridge projects across the Red River are moving forward. Ngô Ngọc Vân, head of Hanoi’s transport construction investment project management agency, said land handover, utility relocation and securing resources remain the main challenges as construction activity increases.
The Tứ Liên Bridge project has received all 62.51 hectares within its land acquisition area, but some locations are still not ready for construction. Some buildings near Alley 310 in Nghi Tàm have yet to be demolished, affecting work on the approach bridge’s pile foundations and piers. A 110 kV power line, substations and other facilities also await relocation.

Construction site of Tứ Liên Bridge.(VietVance)
All 32.6 hectares on the Hanoi side of Ngọc Hồi Bridge have been handed over. On the Hưng Yên side, 22.13 hectares have been handed over, accounting for 97.6% of the required area. The roughly 0.53 hectares remaining involve residential and defense land, graves, and utility relocation. Work is underway at 18 construction fronts, with completed work valued at VND 198.845 billion, or 26.98% of the contract value excluding contingencies.

Land handover on the Hanoi side of Ngọc Hồi Bridge has been completed.(VietVance)
Work is underway at 28 construction fronts on Trần Hưng Đạo Bridge. Completed work is valued at VND 349.2 billion, or 47.96% of the contract value. Some electrical facilities still need to be relocated, and construction permits must be obtained for work within the dike protection zone. Several contractors said the simultaneous start of major projects nearby has caused temporary shortages of materials and skilled workers, driving up construction costs.

About 48% of the contracted work on Trần Hưng Đạo Bridge has been completed.(VietVance)