Khánh Hòa–Buôn Ma Thuột Expressway Costs VND 21.935 Trillion

The 117.5 km Khánh Hòa–Buôn Ma Thuột Expressway has a total investment of VND 21.935 trillion. An inspection on November 19 found that more than 99% of construction work on component project 3 was complete, while component project 2 was nearly 82% complete. Land acquisition, labor shortages and landslide repairs remain challenges for construction and preparations to connect the full route.

VietVance

2 min read

On November 19, Đắk Lắk Vice Chairman Trương Công Thái led a delegation to inspect component projects 2 and 3 of the first phase of the Khánh Hòa–Buôn Ma Thuột Expressway, as well as work to address landslide sites and preparations for a technical connection along the full route. Construction of the expressway began in June 2023. It is 117.5 km long, passing through approximately 32.7 km of Khánh Hòa Province and 84.8 km of Đắk Lắk Province. The four-lane project has a total investment of VND 21.935 trillion.

The first phase of the Khánh Hòa–Buôn Ma Thuột Expressway is 117.5 km long and has a total investment of VND 21.935 trillion.(VietVance)

Component project 3 is more than 48 km long, and more than 99% of the work under its construction contracts has been completed. Under a Vietnamese government resolution dated October 24, 2026, its adjusted funding allocation exceeds VND 5.193 trillion. Cumulative disbursements have reached VND 4.847 trillion, equivalent to 93% of the funding plan. The project owner has completed revisions to the feasibility study report for adding an intelligent transport system and completing the CT.02 interchange. The related cost is estimated at VND 505.683 billion.

Component project 2 is nearly 37 km long and construction is nearly 82% complete. Land acquisition obstacles on sections passing through Yang Mao and Cư Pui, along with labor shortages, are affecting construction. The delegation inspected a landslide site between Km70+535 and Km70+700, then traveled through a road tunnel into Khánh Hòa Province to assess the connections and conditions for technical integration among the three component projects.

Đắk Lắk Vice Chairman Trương Công Thái inspects work to address landslide sites on the Khánh Hòa–Buôn Ma Thuột Expressway.(VietVance)

Trương Công Thái called on project owners and contractors to speed up the remaining work, address landslide sites, and ensure construction quality and safety. For the Km72+500 rest stop, Đắk Lắk has selected an investment plan and is advancing procedures to choose an investor. Once the expressway is completed, the travel distance connecting Khánh Hòa and Đắk Lắk is expected to fall from nearly 200 km to about 117 km.