Thanh Hoa Must Disburse More Than VND 6 Trillion by Year-End

As of November 17, 2026, Thanh Hoa had disbursed VND 14.5927 trillion in public investment funds, or 70.64% of its annual plan. The province aims to reach at least 90% by November 30 and complete the plan by December 30, requiring about VND 6.065 trillion in further disbursements.

VietVance

1 min read

As of November 17, 2026, Thanh Hoa Province had disbursed VND 14.5927 trillion in public investment funds, or 70.64% of its annual plan. The province aims to raise the disbursement rate to at least 90% by November 30. To do so, it must disburse another VND 3.7948 trillion, averaging about VND 1.9 trillion a week. Completing the entire plan by December 30 will require about VND 6.065 trillion in further disbursements.

At a province-wide meeting on November 18, Thanh Hoa Provincial People's Committee Chairman Tô Anh Dũng said public investment disbursement remained slow. He said weekly reviews and publication of results over seven weeks of implementing Plan No. 384/KH-UBND had brought improvements, but the 11% growth target was still not assured. Coordination of data between departments remained weak, and some leaders were inclined to put off action.

The chairman of the Thanh Hoa Provincial People's Committee inspects a project site and urges progress.(VietVance)

Detailed figures previously released by the provincial finance department show that, as of November 9, the 2026 public investment plan funded by the state budget totaled VND 20.65818 trillion, including 2025 funds approved for implementation and disbursement in 2026. The province had allocated VND 20.4306 trillion to specific projects and tasks, or 98.9% of the plan; VND 227.58 billion had yet to be allocated in detail.

Disbursement rates varied considerably across projects. As of November 9, the rate for funds allocated to communes and wards was 72.13%. Of the VND 676.21 billion newly allocated to national target programs in 2026, only VND 20.89 billion had been disbursed, a rate of 3.09%. Tô Anh Dũng called on departments and local authorities to track each project's progress, address obstacles involving procedures, land clearance and construction, and verify the volume of work completed.

Source: VietVance