Lai Uyên Substation and Connection Project Energized on November 21
The 220 kV Lai Uyên substation and connection project in what is now Bàu Bàng commune, Ho Chi Minh City, was energized on November 21, 2026. This phase includes one 250 MVA transformer and about 520 meters of connection lines. The project will support electricity supply to Ho Chi Minh City and surrounding areas.
Vietnam’s Lai Uyên 220 kV substation and connection project was energized on November 21, 2026. The project is located in Cây Sắn hamlet, Lai Uyên township, Bàu Bàng district, formerly Bình Dương province, and is now part of Bàu Bàng commune, Ho Chi Minh City. The National Power Transmission Corporation (EVNNPT) is the project investor, and the Southern Power Projects Management Board (SPMB) manages the project.

The Lai Uyên 220 kV substation was energized on November 21, 2026.(VietVance)
The substation is designed for two 250 MVA transformers. One has been installed in this phase, with space reserved for the second. The 220 kV side is planned to have 10 bays, six of which have been equipped in this phase. The 110 kV side is planned to have 15 bays, six of which have been equipped in this phase. The remaining bays are reserved.
The connection project includes two sections of 220 kV double-circuit line, totaling about 520 meters, linking the new substation to both circuits of the existing Chơn Thành–Bến Cát–Mỹ Phước 220 kV line. The substation is also equipped with control, protection, metering, communications and monitoring systems.
Following energization, the project will be operated by Ho Chi Minh City Power Corporation. It is intended to meet electricity demand in Ho Chi Minh City and surrounding areas, ease the load on existing 220/110 kV transformers and 110 kV lines in the area, and improve the reliability and safety of the power supply.