About 20% of Land Acquired for Lào Cai–Hà Nội–Hải Phòng Railway

Vietnam’s Ministry of Construction says about 515 hectares have been acquired and 131 hectares handed over for the Lào Cai–Hà Nội–Hải Phòng railway. Only 14.4% of the project’s 2026 land acquisition funding had been disbursed by the end of October, prompting the ministry to call for faster progress.

VietVance

2 min read

Vietnam’s Ministry of Construction reported that the Lào Cai–Hà Nội–Hải Phòng railway project is expected to require the acquisition of more than 2,529.58 hectares across six provinces and cities. At the time of the announcement, about 515.01 hectares had been acquired, or 20.36% of the planned area; about 131 hectares had been handed over, or 5.18%. The land acquired and handed over was mainly agricultural and public land. The ministry said land acquisition and site handover remained slow in some localities.

AI-generated illustration of the Lào Cai–Hà Nội–Hải Phòng railway project.(VietVance)

Progress varies considerably among localities. Hưng Yên has acquired 99.05% of its planned area and handed over 95.83%; Hải Phòng has acquired 83.91% but handed over only 3.67%. Lào Cai has acquired 3.11% and handed over 0.76%. The areas acquired and handed over in Phú Thọ, Bắc Ninh City and Hà Nội account for 0.95%, 6.45% and 2.56% of their respective planned areas.

The project’s 2026 land acquisition funding plan totals VND 13.847 trillion. According to reports from the project owner, the Railway Project Management Board, and local authorities, about VND 1.999 trillion had been disbursed by the end of October, or 14.4%. Cumulative disbursement is expected to reach about VND 5.964 trillion, or 43%, by the end of 2026, leaving about VND 7.883 trillion that may not be fully disbursed during the year. The ministry urged local authorities to accelerate disbursement and aim to complete land acquisition for agricultural land, forest land and some public land by December 31, and for residential land, resettlement areas and the remaining land, along with the relocation of related facilities, by June 30, 2027.

The ministry also directed the project owner to speed up the selection of technical design consultants, identify the land needed for the remaining works as soon as possible and hand over the boundaries to local authorities for land acquisition. The project has a main line of about 363 kilometers and branch lines of about 63 kilometers, passing through Lào Cai, Phú Thọ, Hà Nội, Bắc Ninh, Hưng Yên and Hải Phòng. Construction of the project’s first component began on December 19, 2025. On August 24, the National Assembly passed a resolution adjusting the project’s investment policy, raising its preliminary total investment from VND 203.231 trillion to VND 289.339 trillion.