Key Long Thanh Airport Works Expected to Be Delayed Until June 2027

Airports Corporation of Vietnam says work completed on Component 3 of Long Thanh International Airport’s first phase accounts for 88.63% of the contract value, but the component cannot be fully completed in 2026 as planned. Some key works are expected to be completed or finish trial runs in June 2027. Standing Deputy Prime Minister Phạm Gia Túc has ordered the company to report on progress within a week of a November 25 meeting.

VietVance

1 min read

On November 25, Vietnam’s Standing Deputy Prime Minister Phạm Gia Túc chaired a meeting on progress in the first phase of Long Thanh International Airport. The project investor, Airports Corporation of Vietnam (ACV), said the value of work completed on Component 3 had reached VND 76.9538 trillion, or 88.63% of the contract value. Disbursements totaled VND 49.5073 trillion, or 57%.

ACV assessed that Component 3 could not be fully completed in 2026 under the contractual schedule. Key works, including the passenger terminal, Cargo Terminal 1, parking facility and airport management system, are expected to be completed or finish trial runs in June 2027. ACV proposed considering an extension of the first phase’s implementation period to 2027–2028; the change remains subject to review by the competent authorities.

The main obstacles listed by ACV include materials and equipment whose manufacturers, models or places of origin differ from those specified in contracts, with approval procedures for the changes still incomplete; construction drawings for some completed and accepted works that differ from the approved technical designs; and some works that began before their construction drawings were approved. ACV said resolving these issues is necessary for acceptance of the works and an operating licence.

Phạm Gia Túc instructed ACV to review the remaining work and set completion milestones for construction, equipment installation and trial runs. ACV must report to the government and submit the report to the Ministry of Construction within one week of the November 25 meeting. The ministry must report project progress to the government by December 10, 2026, and compile the obstacles and proposed solutions by December 15. He stressed that the airport could begin operations only after meeting acceptance and safety requirements.