Long Thanh Airport Plans 30–40 Daily Flights During 2027 Lunar New Year

Airports Corporation of Vietnam plans to begin phased operations at Long Thanh Airport at midnight on December 24, 2026. The first phase is expected to handle 20–30 flights a day, rising to 30–40 during the 2027 Lunar New Year travel peak as the airport takes on some demand from Tan Son Nhat Airport.

VietVance

2 min read

Airports Corporation of Vietnam (ACV) plans to begin operating Long Thanh International Airport in phases from midnight on December 24, 2026. The first phase will run through the end of March 2027, with an initial 20–30 flights a day expected, equivalent to about 6%–10% of design capacity. During the 2027 Lunar New Year travel peak, the airport is expected to handle 30–40 flights a day.

Rendering of Long Thanh International Airport.(VietVance)

Nguyễn Đăng Minh, head of operations at Long Thanh International Airport, said three domestic airlines—Vietnam Airlines, Vietjet Air and Vietravel Airlines—have registered to operate there, although flight numbers are expected to be low at first. With demand likely to rise during Lunar New Year and few slots available to airlines at Tan Son Nhat Airport, ACV plans to shift some flight demand to Long Thanh.

Facilities planned to enter service in the first phase include the T1 and T2 connecting roads, the main road, an overpass, an access road to the terminal forecourt, a parking garage, a remote parking area and a non-stop toll collection system. Facilities and equipment in the terminal’s west wing, central area and part of its north wing will also enter service. The west wing will serve domestic and international passengers, while part of the north wing will be reserved for international passengers.

The airfield is scheduled to open runway No. 1, parallel and connecting taxiways, and aircraft parking aprons. ACV said two runways and some related works are ready for operation. Runway No. 1 and some airfield facilities were used for the first commercial flight to land at Long Thanh Airport on December 19, 2025. Connecting roads and other projects funded by the company are still being completed and are expected to largely meet schedule requirements before December 24, 2026.

Vietnam Airlines said it has submitted its Long Thanh Airport flight schedule to ACV and expects to complete its formal plan in early December 2026. Whether it adds flights during Lunar New Year will depend on actual passenger demand.

Source: VietVance