Phu Quoc Light Rail Project Deploys 33-Ton Automated Rail Welding Machine
The Phu Quoc light rail project has deployed a 33-ton mobile automated rail welding machine. The contractor says it can weld more than 20 rail joints a day under suitable site conditions, with productivity three to four times that of manual welding. More than 11 km of rail had been laid by the end of October 2026.
The Phu Quoc light rail project began using a 33-ton mobile automated rail welding machine on November 5, 2026, the first time equipment of this kind has been put into use in Vietnam. The machine travels along installed rails and automatically welds joints at the construction site. It uses electrical heating and pressure to join the rail ends. Automated welding takes about 3 to 4 minutes per joint, after which the joint is ground, inspected and finished.

The 33-ton automated rail welding machine in use at the Phu Quoc light rail construction site.(VietVance)
Nguyễn Huy Thanh, a representative of the rail welding contractor, said that under suitable site conditions, the machine can weld more than 20 joints a day, equivalent to 250 to 300 meters of single-track rail. With traditional methods, a crew of 6 to 8 people welds an average of 4 to 6 joints a day, or about 8 at most. The automated machine requires only 3 operators and delivers about three to four times the labor productivity of manual welding. All its operators are Vietnamese workers who previously worked on railway projects in Myanmar and received training before starting work on Phu Quoc.

The automated rail welding machine takes about 3 to 4 minutes to weld one rail joint.(VietVance)
Nguyễn Tất Đạt, head of the rail supply and installation contract package, said more than 11 km of the project's 35 km of rail had been laid by the end of October 2026. By the time of publication, the automated machine had welded more than 1 km of rail, and about 1,300 engineers and workers were at the construction site. All bored piles in the bridge and tunnel areas have been completed, while construction of the station structures continues. The tunnel leading to Phu Quoc Airport has completed its reinforced concrete structure and is being prepared for track installation.

More than 11 km of rail had been laid on the Phu Quoc light rail project by the end of October 2026.(VietVance)
The Phu Quoc light rail line is nearly 17.6 km long and has 6 stations. Construction began in December 2025, with total investment of about VND 9 trillion under a BOT arrangement. The project is scheduled for completion in the second quarter of 2027, with rail work due to be finished before March 2027. Trial runs are planned for July 2027, followed by commercial service in November 2027 to serve the APEC meeting. Once the line is operating, the journey from Phu Quoc International Airport to the APEC Conference and Exhibition Center in the south of the island is expected to take 18 to 20 minutes.