Cam Lộ–La Sơn Expressway Expansion May Be Delayed Until 2027
Construction on Vietnam’s Cam Lộ–La Sơn expressway expansion has reached nearly 49% of the contract value. The project management board plans to seek approval to delay its opening from 2026 to 2027 and reduce total investment by nearly VND 723 billion. Delayed land handover, prolonged rain and asphalt shortages have slowed work.