Khánh Hòa LNG Power Plant Signs Italian Gas Turbine Equipment Contract

On November 20, a consortium led by Vietnam’s Trungnam signed an equipment supply contract with Italy’s Ansaldo Energia and a memorandum of understanding with China’s Shanghai Electric. The Cà Ná LNG power plant in Khánh Hòa Province has a planned capacity of 1,500 MW and an estimated investment of nearly $2.2 billion. It is targeted to begin operating in 2030.

VietVance

1 min read

On November 20, a consortium led by Trungnam signed an equipment supply contract with Italy’s Ansaldo Energia S.p.A. and a memorandum of understanding with China’s Shanghai Electric for the Cà Ná LNG power plant project in Khánh Hòa Province. The project is targeted to begin operating in 2030.

Trungnam signed an equipment supply contract with Italy’s Ansaldo Energia.(VietVance)

Under the contract, Ansaldo Energia will supply two GT36 gas turbines, generators and related auxiliary equipment. The GT36 uses two-stage combustion technology designed to maintain efficiency at both full and partial load while controlling nitrogen oxide emissions. Trungnam Chairman Nguyễn Tâm Thịnh said the two companies would also study ways to improve gas power plant efficiency, optimize operations and use cleaner fuels in the future.

Shanghai Electric signed a memorandum of understanding and is expected to participate in supplying steam turbines, steam turbine generators, heat recovery steam generators, condensers and related auxiliary systems. This equipment can use waste heat from gas turbine exhaust to generate additional electricity. The two sides still need to agree on technical, commercial and cooperation arrangements.

Shanghai Electric is expected to participate in supplying steam turbines, heat recovery steam generators and other equipment for the Cà Ná power plant.(VietVance)

The Cà Ná power plant has a planned capacity of 1,500 MW and an estimated total investment of nearly $2.2 billion. The winning bidder was a consortium of Trungnam and Sideros River. Once operational, the project is expected to supply about 9 billion kWh of electricity a year to Vietnam’s national grid.

Source: VietVance