Long Thanh Airport’s Second Runway Set for Calibration Flights in Early December
Airports Corporation of Vietnam plans to conduct calibration flights on Long Thanh International Airport’s second runway in early December 2026. The airport is scheduled to begin commercial operations on December 24, initially using only its first runway.

Airports Corporation of Vietnam (ACV) said it plans to conduct calibration flights on Long Thanh International Airport’s second runway in early December 2026. The runway is designated Runway No. 3 in the project. After the flights, ACV will complete the relevant procedures and publish the information through the aeronautical information notice system in preparation for bringing it into service.
ACV said both runways and some airfield facilities are now ready for operation. Runway No. 1 and some of those facilities served the first commercial flight to land at Long Thanh Airport on December 19, 2025. Information on Runway No. 1 has also been published through the aeronautical information notice system.
Long Thanh Airport is scheduled to begin commercial operations on December 24, 2026. During the initial period, from that date through the end of March 2027, traffic is expected to reach about 6% to 10% of design capacity, and the airport will use only Runway No. 1. ACV proposed adding a second runway during the project’s first phase in 2024. The change was approved in late March 2025, and construction began that May. The second runway is the same size as Runway No. 1, measuring 4 kilometers long and 75 meters wide.
Construction of Long Thanh Airport began on January 5, 2021. The project is divided into three phases, with an initially estimated total investment of about 336.6 trillion Vietnamese dong, equivalent to more than US$16 billion. The first phase was approved in November 2020 with an investment of 109.111 trillion Vietnamese dong and a designed annual capacity of 25 million passengers and 1.2 million tonnes of cargo. Once all three phases are complete, the airport’s designed annual capacity will reach 100 million passengers and 5 million tonnes of cargo.
Source: VietVance