Deputy PM Urges Timely Completion of Four Transport and Port Projects in Cà Mau
Vietnam’s deputy prime minister inspected four major transport and port projects in Cà Mau on November 21, urging faster construction and quality assurance. The project owner said land clearance was complete. At the time of reporting, work completed on the four projects represented 9% to 22% of their contract values, and 97.4% of planned 2026 funding had been disbursed.