Deputy PM Urges Timely Completion of Four Transport and Port Projects in Cà Mau

Vietnam’s deputy prime minister inspected four major transport and port projects in Cà Mau on November 21, urging faster construction and quality assurance. The project owner said land clearance was complete. At the time of reporting, work completed on the four projects represented 9% to 22% of their contract values, and 97.4% of planned 2026 funding had been disbursed.

VietVance

2 min read

On November 21, Vietnamese Deputy Prime Minister Lê Tiến Châu led a delegation to inspect major projects in Cà Mau Province and met with provincial authorities, project owners and contractors. The projects include the Cà Mau–Cái Nước and Cái Nước–Đất Mũi expressways, the road to Hòn Khoai Island and the dual-use Hòn Khoai general port.

Vietnamese Deputy Prime Minister Lê Tiến Châu meets with project owners and contractors.(VietVance)

Lê Tiến Châu commended contractors’ efforts to accelerate construction. He called on local authorities and project stakeholders to resolve obstacles promptly, add workers, machinery and equipment, and increase capacity to transport materials so that construction can continue without interruption, quality is maintained and the projects are completed on schedule. He also asked local authorities to inspect progress regularly and promptly report issues requiring resolution to the relevant authorities.

A representative of the project owner, Tổng công ty Xây dựng Trường Sơn (Binh đoàn 12), said land clearance was complete. Localities in the surrounding area have supported the supply of 6 million cubic meters of stone, and 20 million cubic meters of sand for filling have also been secured. Current work focuses on roadbed filling, pile foundations and concrete components.

At the time of reporting, completed work on the Cà Mau–Cái Nước expressway was valued at 5.194 trillion Vietnamese dong, or 22% of its contract value; the figure for the Cái Nước–Đất Mũi expressway was 2.712 trillion dong, or 11%. Completed work on the road to Hòn Khoai Island was valued at 1.946 trillion dong, or 9%, while work on the general port was valued at 1.5 trillion dong, or 10.6%. Of the funding planned for 2026, 97.4% had been disbursed.

Binh đoàn 12 said it had launched a construction drive for the two expressways and the road to the island, running through December 31, 2026. Its targets are 7.4 trillion dong in construction output, 7.7 trillion dong in accepted work and 7.4 trillion dong in payments. Cà Mau provincial leaders said they would continue helping project owners resolve issues with the supply of construction materials.

Source: VietVance