Three Red River bridges ahead of revised construction schedules
According to Hanoi’s Department of Construction, construction work on the Trần Hưng Đạo, Hồng Hà and Mễ Sở bridges has exceeded revised targets. The Trần Hưng Đạo Bridge is scheduled for completion before June 30, 2027.
According to a report by Hanoi’s Department of Construction, the value of construction work on the Trần Hưng Đạo, Hồng Hà and Mễ Sở bridges has exceeded revised targets. They are among seven Red River bridge projects under way. The three bridges will respectively connect central Hanoi with the east of the city, serve the Capital Region Ring Road 4 project, and link Hanoi with Hưng Yên.
Construction work on the Trần Hưng Đạo Bridge has exceeded VND 336.6 billion, reaching 54.2% of the contract value and surpassing the revised target by 4.3 percentage points. On the afternoon of November 16, construction teams began installing the first steel arch sections of the main bridge. By early November, all 128 bored piles and seven pier foundations for the main bridge had been completed. The project began in October 2025, has a total investment of VND 1.6226 trillion and is scheduled for completion before June 30, 2027.

Construction work on the Trần Hưng Đạo Bridge has reached 54.2% of the contract value.(VietVance)
Construction work on the Hồng Hà Bridge has reached nearly VND 212.6 billion, or 53.4% of the contract value, exceeding the revised target by 0.9 percentage points. All 941 bored piles and 69 of the 70 pier foundations have been completed. The bridge and its approach roads are approximately 6 km long. The project began on October 31, 2025, has a total investment of VND 980 billion and is part of Capital Region Ring Road 4.

Construction work on the Hồng Hà Bridge, part of Capital Region Ring Road 4, has reached 53.4% of the contract value.(VietVance)
Construction work on the Mễ Sở Bridge has exceeded VND 161.8 billion, reaching 50.1% of the contract value and surpassing the revised target by 1.6 percentage points. All 116 bored piles in the main bridge area have been completed. The bridge is approximately 2.024 km long, beginning in Hồng Vân commune in Hanoi and ending in Mễ Sở commune in Hưng Yên. Component project 3 of Capital Region Ring Road 4, which includes the Hồng Hà and Mễ Sở bridges, is scheduled to open to traffic on a trial basis before July 2027.

Construction work on the Mễ Sở Bridge has reached 50.1% of the contract value.(VietVance)
Source: VietVance