Hue Seaside Park 72% Complete, Set to Open in Late December
Hue’s Thuận An seaside multifunctional cultural park, an investment of nearly VND 118 billion, was about 72% complete as of November 21, 2026. The project owner expects to hand over and open the main facilities in late December for Hue’s New Year 2027 celebrations.
Construction of Hue’s Thuận An seaside multifunctional cultural park was about 72% complete as of November 21, 2026. The project has a total investment of nearly VND 118 billion and covers nearly 14.48 hectares of cleared coastal land. The project owner expects to hand over and open the seaside central square and other main facilities in late December, in time for Hue’s New Year 2027 celebrations.

Hue’s Thuận An seaside multifunctional cultural park has a total investment of nearly VND 118 billion.(VietVance)
According to the project owner, Ban QLDA Đầu tư xây dựng Bắc Sông Hương, the central square’s concrete base is 95% complete and the service building is 85% complete. Pipes for the underground electrical system have been laid, while about 15% of the landscaping has been planted. With construction taking place during central Vietnam’s rainy season, the owner has asked contractors to maintain staffing and equipment and advance the work when weather permits.

As of November 21, 2026, construction of the park was about 72% complete overall.(VietVance)
The seaside central square covers more than 5,011 square meters and is planned for festivals, cultural and tourism events, and large community gatherings. Two parks beside the square have a combined area of 3,441 square meters. The project also includes a 190-meter protective embankment for the square, two internal roads measuring 229 meters in length, and lighting, water supply and drainage facilities.
The site is affected by strong winds and high tides during the rainy season, and sea sand has buried part of the central square under construction. The park borders Hue’s coastal road and the Thuận An bridge across the sea inlet, which is already in operation. Once open, the project is expected to add public gathering space and tourism facilities; its effect on the local economy remains to be seen after operations begin.

The project owner expects to hand over the seaside central square and other main facilities in late December for Hue’s New Year 2027 celebrations.(VietVance)
Source: VietVance