Vietnamese Engineering Teams Gain Expertise in Building Large Bridges

From Mỹ Thuận 1, completed in 2000, to Mỹ Thuận 2, designed and built by Vietnamese teams, the division of technical work in Vietnam’s large bridge projects has changed. Rạch Miễu 2 and the Phước An bridge, still under construction, illustrate the challenges of building across rivers, coordinating materials and controlling bridge structures.

VietVance

2 min read

Completed in 2000, Mỹ Thuận 1 was mainly designed, supervised and built by an Australian team, with the Vietnamese team working as a subcontractor. On Rạch Miễu 1, which broke ground in April 2002, a Vietnamese team designed a cable-stayed bridge and served as its general contractor for the first time, though Swiss specialists were still needed to install the cables. Later, a Vietnamese team handled project planning, design and all construction work on Mỹ Thuận 2, including cable tensioning. The project cost more than VND 500 billion and has a 350-meter main span.

The main bridge of Mỹ Thuận 2 is 1.9 kilometers long. A Vietnamese team carried out all construction work, including cable tensioning.(VietVance)

Each main pier foundation on Mỹ Thuận 2 has 26 bored piles, each 2.5 meters in diameter and approximately 110 to 116 meters deep. Phan Văn Quân, the construction consortium’s site manager, said the original reverse-circulation drilling plan did not meet requirements because the riverbed geology differed from expectations. After reviewing the plan, the engineering team switched to another drilling method. During construction of the girders and cables, the team also had to use measurements taken after each round of concrete casting and cable tensioning to check the structure’s condition before proceeding.

Construction of Rạch Miễu 2 had to proceed while boats continued to use the river. Cấn Mạnh Hùng, a representative of the construction consortium, said the project took nearly three years. At its peak, it involved more than 350 workers, 70 engineers and 35 work fronts. Any mismatch in equipment or material supply would affect subsequent work.

The main bridge of Rạch Miễu 2 is 1.97 kilometers long and 17.5 to 21.5 meters wide.(VietVance)

The Phước An bridge connects Ho Chi Minh City and Đồng Nai. The bridges in the overall project extend approximately 4.38 kilometers, and the main bridge uses a structure in which a prestressed concrete box girder and low-tower stay cables share the load. Huỳnh Giáp Nhân, head of Trungnam E&C, said measurement results and navigation safety must be checked at every construction stage. The main span has been joined, and tensioning of 24 cable bundles at the two main piers is complete. The consortium’s portion of the work is approximately six months ahead of the contractual schedule. The bridge is expected to open in May 2027.

The main bridge of Phước An uses an extradosed girder structure and is expected to open in May 2027.(VietVance)

Source: VietVance