Đại Ngãi 1 Bridge Pylon Nearly 81% Complete
As of November 2026, construction of the Đại Ngãi 1 cable-stayed bridge pylon had reached its 22nd segment, with pylon work nearly 81% complete. The bridge has a 450-meter main span. The wider Đại Ngãi Bridge project has an investment of nearly VND 8 trillion and is scheduled to begin operation in June 2028.
Tập đoàn Đèo Cả said on November 21, 2026, that construction of the P23 pylon of the Đại Ngãi 1 cable-stayed bridge had reached its 22nd segment, with pylon work nearly 81% complete. The contractor consortium currently has 23 work fronts, with more than 350 personnel and 85 pieces of machinery and equipment deployed. Nguyễn Kỳ Nam, deputy general director of the project executive board, said the bridge’s 450-meter main span was the second longest in Vietnam as of November 2026.

Construction site of the Đại Ngãi Bridge in March 2026.(VietVance)
Construction of the bridge began in January 2025. Bored pile work was completed between May and November of that year, and the P23 pylon footing was completed in January 2026. Pylon construction began in March 2026 and is scheduled for completion in April 2027. The entire Đại Ngãi Bridge project is scheduled to be completed and begin operation in June 2028.
Ban Quản lý dự án 85 is the investor in the Đại Ngãi Bridge project, which has a total investment of nearly VND 8 trillion and extends more than 15 kilometers. It includes two bridges, Đại Ngãi 1 and Đại Ngãi 2. The construction contract for Đại Ngãi 1 and the approach roads at both ends is worth about VND 3.868 trillion and is being carried out by a contractor consortium led by Tập đoàn Đèo Cả.
According to Tập đoàn Đèo Cả, Đại Ngãi 1 has a cable-stayed design with spans of 210, 450 and 210 meters and two A-shaped main pylons, each 110 meters tall. Once the project is completed, traveling from Cà Mau to Ho Chi Minh City via the bridge will shorten the journey by about 80 kilometers compared with the current route along National Highway 1A.